Construction Delay Analysis Summary

Summary

A window analysis was conducted for Navillus / MLJ JV, covering Windows 8 to 13, to evaluate delays from August 11, 2020, to January 25, 2021. The analysis assessed the cumulative impact of delay events, including concrete and debris removal, asbestos removal, and site conditions. The results revealed a total entitlement of 193 calendar days due to these delays, extending the Substantial Completion date to April 22, 2024.

Full Conversation

Rephrase "A window analysis was conducted, covering Windows * through *, to evaluate the delays experienced by Navillus / MLJ JV from August 11th,* (the end of the delays presented in window *) through January 25th,*. The analysis aimed to assess and quantify the cumulative impact of the following delay events: *. Additional Concrete Removal *. Additional Debris Removal *. Additional Asbestos Removal *. Brick Size Clarification *. Different Site Conditions *. Historic Content Change order *. Archaeologist Hold *. Additional Sub-foundation Surveys The results of the analysis revealed a total entitlement of * calendar days due to these delays. Consequently, Navillus / MLJ JV is entitled to an Extension of Time, moving the Substantial Completion date from October 12th,* (as requested in the analysis of windows * to *) to April 22nd,*. "
A window analysis covering Windows * to * was conducted to assess delays faced by Navillus / MLJ JV from August *, *, to January *, *. It quantified impacts from various delay events such as concrete and debris removal, asbestos removal, and site conditions, resulting in a *-day entitlement, extending completion to April *, *.
reorganize "A window analysis was conducted, covering Windows * through *, to evaluate the delays experienced by Navillus / MLJ JV from August 11th,* (the end of the delays presented in window *) through January 25th,*. The analysis aimed to assess and quantify the cumulative impact of the following delay events:"
Here's a reorganized version of the provided analysis:
A window analysis was conducted, covering Windows * through *, to evaluate the delays experienced by Navillus / MLJ JV from August *, * (the end of delays in window *) through January *, *. The analysis aimed to assess the cumulative impact of delay events:
*. Additional Concrete Removal
*. Additional Debris Removal
*. Additional Asbestos Removal
*. Brick Size Clarification
*. Different Site Conditions
*. Historic Content Change Order
*. Archaeologist Hold
*. Additional Sub-foundation Surveys
The analysis revealed a total entitlement of * calendar days due to these delays. Consequently, Navillus / MLJ JV is entitled to an Extension of Time, moving the Substantial Completion date from October *, * (as requested in the analysis of windows * to *) to April *, *.