Project Delay Notice Clarification

Summary

The Owner acknowledges receipt of Contractors early warning notice GNBY-ENW-003 dated 13 September 2024 regarding the delay in the delivery of Protection Panels due to subcontractor performance. The projected delivery date is now February/March 2025, endangering the energisation date for the 33kV side of the project. The Contractor has requested an increase in the total Contract Price, extension of G99 Completion, extension of key completion dates, and an increase in Subcontractor’s total costs if notified by the Subcontractor. Could you provide more details on the contract terms related to delays and penalties? This will help in understanding your options better.

Full Conversation

The Owner acknowledges receipt of Contractor's early warning notice GNBY-ENW-* dated * September * ("EWN") regarding the delay with the delivery of Protection Panel Supply which paired with performance of the subcontractor. Currently Projected delivery date of these Protection Panels is of falling to February/March *, which endangering the energisation date of the 33kV side of the project against the current programme.
It looks like you are dealing with a project delay issue caused by a subcontractor's performance, which may affect the energisation date of a 33kV project. Here’s how you might improve your answer for clarity and conciseness:
---
The Owner acknowledges receipt of Contractor's early warning notice GNBY-ENW-* dated * September * ("EWN") regarding the delay in the delivery of Protection Panels due to subcontractor performance. The projected delivery date is now February/March *, endangering the energisation date for the 33kV side of the project.
---
Could you provide more details on the contract terms related to delays and penalties?
The Owner acknowledges receipt of Contractor's early warning notice GNBY-ENW-* dated * September * ("EWN") regarding the delay with the delivery of Protection Panel Supply which paired with performance of the subcontractor. Currently Projected delivery date of these Protection Panels is of falling to February/March *, which endangering the energisation date of the 33kV side of the project against the current programme. Thereby, in brief, Contractor requested: • Increase the total of the Contract Price • Extension of G99 Completion • Extension of key completion date • If notified by the Subcontractor, increase the Subcontractor’s total costs
Hi there! Here's an improved version of your interaction for clarity and conciseness:
---
The Owner acknowledges receipt of Contractor's early warning notice GNBY-ENW-* dated * September * ("EWN") regarding the delay in the delivery of Protection Panels due to subcontractor performance. The projected delivery date is now February/March *, endangering the energisation date for the 33kV side of the project.
The Contractor has requested:
- Increase in the total Contract Price
- Extension of G99 Completion
- Extension of key completion dates
- Increase in Subcontractor’s total costs if notified by the Subcontractor
---
Could you provide more details on the contract terms related to delays and penalties? This will help in understanding your options better.
check and improve:
Sure, here's an improved version of your interaction:
---
Question: Hi! I'm with FreeLawChat, here to assist you with your legal issue. May I know your name, please?
Answer: The Owner acknowledges receipt of Contractor's early warning notice GNBY-ENW-* dated * September * ("EWN") regarding the delay in the delivery of Protection Panels due to subcontractor performance. The projected delivery date is now February/March *, endangering the energisation date for the 33kV side of the project.
Question: It looks like you are dealing with a project delay issue caused by a subcontractor's performance, which may affect the energisation date of a 33kV project. Here’s how you might improve your answer for clarity and conciseness:
---
The Owner acknowledges receipt of Contractor's early warning notice GNBY-ENW-* dated * September * ("EWN") regarding the delay in the delivery of Protection Panels due to subcontractor performance. The projected delivery date is now February/March *, endangering the energisation date for the 33kV side of the project.
---
Could you provide more details on