Summary

A contractor may be liable for excess costs if a government terminates a contract and hires a new contractor at a higher rate. The clause specifies that the contractor is responsible for any amount exceeding the original contract cost, including costs related to awarding, assigning, and engaging another contractor. Jurisdiction-specific regulations may apply, so its important to consider the location of the contract issue.

Full Conversation

A
Could you please provide more details about your issue with the contract? Specifically, what aspect of the contract termination is concerning you?
Refer to the below clause. If the government choose to terminate the contract of 1 year period that is paid monthly with a contractor, and the government engages in a new contract with higher monthly rate, is the previous contractor responsible for paying the difference in monthly rate for the remainder of months in the original contract period? "Without prejudice to any rights and remedies which Government has or may have against the Contractor (including such rights of action as shall have accrued to Government prior to the termination), if the Contract is terminated by Government: (b) the Contractor shall be liable for any amount in excess of the overall cost of the Contract incurred by Government in awarding, assigning and/or engaging another Contractor to complete the uncompleted Services;"
Based on the clause you provided, the previous contractor may be responsible for the difference in the overall cost incurred by the government in engaging a new contractor. The key points are:
- The contractor is liable for any amount exceeding the original contract cost.
- This includes costs related to awarding, assigning, and engaging another contractor.
Where is this contract issue taking place? This can help in understanding any jurisdiction-specific regulations that might apply.